Transitional Housing Project in Kam Tin
At Lot 2160 RP (Part) in D.D. 106 and Adjoining Government Land in Kam Tin, Yuen Long, New Territories
Capacity in the Project: MiC Term Consultancy under Llewyn Davies Hong Kong Ltd MiC Designer (7 months up to now)
Contract commencement & completion with OP granted (month/year)
-Contract Commencement on: Nov 2021
- Contract completion (with OP granted) on: Current Project – Target Main Contract start Q2 2022
No and Types of MiC/ storeys / GFA / Flat no / number of blocks(s) :
Steel MiC / 4 storey / 248,400 ft2 / 1,028 units /6 nos of blocks with Amenity building and ancillary services.
Project Sum ($M): HKD$ 576.3M (Transport and Housing Bureau approved budget)
Responsibility:
MiC Designer to assist Project Architect to develop the design of MiC layout, connection details, interior design and fitting out of the project. Scope includes initial MiC Concept design, detailed design, logistic consideration, buildability consideration, tender document
and technical specifications / drawings preparation.